Commercial (New contruction/Additions/Alterations)

  • Two sets of drawings with engineer or architect seal to include site plan, TOPO plan, plus complete building drawings with plumbing, HVAC, electrical, framing, and foundation, etc.
  • Complete Building Application
  • A copy of current state G and C License
  • Site Plan to show water lines, gas lines, sewer lines, parking spaces, all signs, lift station if applicable, etc.
  • TOPO plan must show all elevation and drainage, etc.
  • Compaction results (if needed) to be turned in prior to any foundation or footing inspection
  • Site plan must be submitted to city engineer and approved prior to Building Application Approval
  • Building construction must comply with architect of engineer design. Change orders must be submitted prior to inspection
  • Building drawings must be approved by Fire Marshall prior to permit being issued
  • Landscape drawings detailed with tree and planting description must be turned in for planning commission approval prior to final inspection
  • Commercial final must be performed by City Fire Marshall, City Engineer, and Inspection Department before a Certificate of Occupancy can be issued
  • Residential/Commercial contractors and sub contractors must have a City of Calera Business License prior to performing work

Permits will be ready for pickup 3 weeks after submission.

Back to top

 

Residential (New construction/Additions/Alterations)

  • One sets of drawings
  • Permit Application completely filled out front and back
  • Copy of Current Homebuilders License
  • Plot plan stamped by an architect or engineer
  • Form surveys must be turned in before the final slab inspection inspection is done. This must be done by an engineer.
  • Signed copy from Health Department on installation acceptance of private sewage disposal systems at time of application submittal. 
  • Residential/Commercial contractors and sub contractors must have a City of Calera Business License prior to final inspector being called in. This will be checked.

Permits will be ready for pickup 72 hours after submission. Proof of Utility Tap fees will be required at the time of purchase

Back to top